The 2024 revision of Government Auditing Standards replaced quality control with a risk-based system of quality management. Every GAGAS audit organization needed one in place by December 15, 2025, and the official accountable for it has to evaluate it within a year, then at least annually after that. Here is what the evaluation involves, what to document, and a checklist to work from.

Key dates
Dec 15, 2025
System designed and implemented
Dec 15, 2026
First evaluation completed
Every year after
Evaluate at least annually
Every year, everyone
Written independence affirmation
GAO-24-106786 · chapter 5
What changed

From a set of controls to a system you manage by risk.

Under the 2018 standards, an audit organization documented its quality control policies and had them peer reviewed. The 2024 standards ask more: decide what quality means for your office, find what could get in the way, and show that your responses work.

01

Objectives, risks, responses

Set quality objectives, identify quality risks that have a reasonable possibility of occurring and of hurting an objective, and design responses (your policies and procedures) that address them. GAGAS 5.19–5.23

02

Your own monitoring

You need monitoring activities of your own, such as inspecting completed engagements. The standard is explicit that a peer review is not a substitute for monitoring. GAGAS 5.105

03

Sized to your office

How formal the system is depends on your circumstances, including the size of the office and the complexity of its engagements. A two-person office and a sixty-person office will not look the same. GAO-26-108710

The components

Six components, and two processes that run them.

Paragraph 5.03 lists six components that need quality objectives, plus two components that are processes: one that sets up the system and one that checks it.

Component 1

Governance and leadership

Who is accountable for quality, how leadership shows its commitment, and how resources are planned around it.

Component 2

Independence, legal and ethical requirements

Identifying and responding to threats to independence, and at least annually getting a written affirmation from everyone required to be independent. GAGAS 5.48

Component 3

Acceptance, initiation and continuance

How engagements are taken on, started and continued, including whether you have the people and time to do them properly.

Component 4

Engagement performance

Direction, supervision and review of the work, consultation on difficult matters, differences of opinion, and engagement quality reviews where they apply.

Component 5

Resources

People, technology and intellectual resources: competence, CPE, and the tools and templates the work depends on.

Component 6

Information and communication

Getting relevant, reliable information to the people who need it, inside the office and out, so the system actually operates.

Process

Risk assessment process

Setting the quality objectives, identifying and assessing the quality risks, and designing and putting the responses in place.

Process

Monitoring and remediation process

Checking that the system works, evaluating findings for deficiencies and their causes, and fixing them. Its results are what the annual evaluation weighs.

The annual evaluation

One official, one point in time, one documented conclusion.

The senior-level official assigned responsibility and accountability for the system evaluates it as of a point in time, at least annually, and concludes on whether it gives the office reasonable assurance that its objective is being achieved. GAGAS 5.128

01

Gather the monitoring results

The monitoring you performed, what it found, and the remedial actions already taken. GAGAS 5.125

02

Evaluate the deficiencies

Judge each one's severity and pervasiveness by investigating its underlying cause and its effect, alone and together. GAGAS 5.110

03

Weigh the risk assessment

Consider your objectives, risks and responses, and how well the responses actually address the risks. GAGAS 5.129

04

Conclude and document why

Reach one of three conclusions and write down the basis for it. GAGAS 5.128, 5.133

The three possible conclusions

  1. Reasonable assurance. The system provides reasonable assurance that its objective is being achieved.
  2. Except for. Except for identified deficiencies with a severe but not pervasive effect, the system provides reasonable assurance.
  3. No reasonable assurance. The system does not provide reasonable assurance that its objective is being achieved.

A severe deficiency does not automatically rule out the first conclusion: if it was remediated and its effect corrected by the evaluation date, the official may still conclude the system provides reasonable assurance. GAGAS 5.131

Checklist

What to have on file by December 15.

Paragraph 5.133 lists what your documentation of the system should include. This checklist follows it, with the annual independence affirmations added.

  • The senior-level official assigned responsibility and accountability for the system, and anyone assigned operational responsibility, named in writing. GAGAS 5.13, 5.133

  • Your quality management risk assessment: quality objectives, quality risks, and a description of the responses and how they address the risks. GAGAS 5.19–5.23, 5.133

  • Evidence of the monitoring activities you performed, such as inspections of completed engagements. GAGAS 5.90, 5.133

  • Your evaluation of the findings, the deficiencies you identified, and their underlying causes. GAGAS 5.109–5.110

  • Remedial actions for those deficiencies, and your evaluation of how they were designed and implemented. GAGAS 5.119–5.120

  • Communications about monitoring and remediation to the senior-level official. Oral communications count, but document them, for example in meeting minutes. GAGAS 5.125–5.126 · GAO-26-108710

  • This year's written independence affirmations from everyone required to be independent. GAGAS 5.48

  • The conclusion, signed by the senior-level official, and the basis for it. GAGAS 5.128, 5.133

  • A retention period for all of this that is long enough for your peer reviewer to look back over it. GAGAS 5.134

Two things that catch people out

Your last peer review can't stand in for the evaluation. It covers a past period, and GAO's FAQ says the senior-level official cannot rely on a peer review report to evaluate the system.

If the system does not provide reasonable assurance because of severe and pervasive deficiencies, GAO's FAQ says the office should use a modified GAGAS compliance statement (paragraphs 2.16–2.23) until the deficiencies are remediated.

Where UnifiedAudit fits

Do the evaluation in software built around it.

Both products ship with a 30-objective GAGAS starter pack, so you start from the standard's own structure instead of a blank page, and tailor it to your office.

Desktop · free through 2027

UnifiedAudit QM Essentials

A Windows app for the quality-management essentials: the risk-based register, eight pre-written and editable QM policies, independence records and annual affirmations, CPE tracking, the annual evaluation with a signed quality-control report, and a print-ready peer-review packet. Everything stays in one file on your computer.

$575 a year per audit shop after December 31, 2027
Platform · your own Microsoft 365 tenant

UnifiedAudit

Quality management inside the audit system your whole team works in. Each response in the register links to live evidence (peer reviews, internal inspections, QC policies, analytics tests and workflow settings), so its status is current when the evaluation starts. The evaluation records deficiencies by component; signing it locks it and writes it to the audit trail, and the quality-control report exports to Word.

Runs in your own Microsoft 365 and Azure tenant

Sources

This page summarizes the standard to help you plan; it is not the standard. Where they differ, GAGAS governs. Last reviewed November 10, 2026.

See the evaluation done in UnifiedAudit.

A walkthrough takes about thirty minutes: the register, the evidence links, and the signed evaluation, using example data.